Punjab's Rasul technology university project is now estimated at Rs18.9 billion, up from Rs7.6 billion in 2024

The Punjab working party cleared Rs18.862 billion on 13 November for the university at Rasul, Mandi Bahauddin. The same scheme was approved at Rs7.584 billion in December 2024 and Rs9.793 billion in June 2025.

By The Frontier Edit editors3 min read

Share

Share to your story

Sized for Instagram Stories. The link is copied, ready for a link sticker.

Making your story imageA few seconds

Workers on the concrete frame and scaffolding of a multi storey building under construction
Workers on the concrete frame and scaffolding of a multi storey building under construction Photo: Iqro Rinaldi on Unsplash, Unsplash License

A university building project in Mandi Bahauddin now has an approved cost two and a half times what planners first signed off. On 13 November the Provincial Development Working Party of Punjab cleared Rs18.862 billion for infrastructure, academic and operational facilities at the Punjab University of Technology in Rasul. The same scheme went through the working party at Rs7.584 billion in December 2024 and at Rs9.793 billion in June 2025. Each approval has been larger than the last.

Three approvals, one scheme

The first approval came in December 2024, when the scheme was the largest of ten cleared that day, which together came to Rs20.676 billion. The second, at the 85th meeting of the 2024 to 2025 financial year in June 2025, raised the figure by Rs2.209 billion. The Planning and Development Board's release for that meeting lists the scheme as provision of infrastructure and academic facilities at the Rasul university. The third, on 13 November 2026, adds Rs9.069 billion more.

The arithmetic is plain. Rs18.862 billion is 93 percent above the June 2025 figure (18.862 divided by 9.793) and 149 percent above the December 2024 figure (18.862 divided by 7.584). The rise between the first two approvals took six months. The rise between the second and third took nearly seventeen months. Measured by rupees added each month, the later revision is about Rs0.53 billion a month against about Rs0.37 billion a month for the earlier one, so the estimate has not stopped moving. The scheme on its own is now close to the Rs20.676 billion that ten schemes added up to when it was first approved.

None of the notices says why the figure rose. A cost estimate in a development scheme changes when floor area or equipment is added, when prices move between the date of approval and the date of tender, or when the first estimate left items out. The published notices do not separate these. Only the revised project document can show which of them applies, and it is not among the published notices.

What a working party approval means

The working party is the forum where Punjab's planners give a development scheme its technical and financial clearance. Clearance is a permission to proceed to funding, not a payment. Money moves later, through the allocation a scheme receives in the annual development programme and the releases that follow during the year. A revised cost has to return to the working party, which is why this scheme has appeared there three times.

It also means the Rs18.862 billion is a total across the years the work takes, not a figure for one year. A campus of this size is built in phases, and each year's spending depends on the allocation it wins against other schemes. The same meeting cleared Rs126.668 billion in all, and the university accounts for about 15 percent of it (18.862 divided by 126.668). Only the Rs75.987 billion programme of sewerage, drainage and street paving in several cities was larger.

Why a technology campus costs more

The university was set up in 2018 by upgrading the Government College of Technology, Rasul, whose roots go back to a school of engineering founded in 1912. Its own website reports more than 2,500 enrolled students, more than 207 faculty, 15 academic departments and more than 25 undergraduate programmes.

Engineering and computing programmes need building types that a lecture hall campus does not. Laboratories need heavy electrical supply, ventilation, backup power and fixed machinery, and much of that sits in the building budget as well as in the equipment budget. That raises the cost of each square metre, and it raises the cost of getting the first estimate right. A scheme described only as buildings, classrooms and other facilities gives a reader no way to judge how much of the Rs18.862 billion is laboratories and how much is lecture space.

Who gains, who waits

If the campus is built to plan, the gain goes to students in and around Mandi Bahauddin who would otherwise have to travel for an engineering or technology degree. The cost falls on the other schemes waiting for allocation, and on the university itself if buildings are finished faster than faculty and laboratory equipment can be funded to fill them.

What is still unknown is the scheme's intake target, its scope by building and its yearly spending schedule. The next marker is the 2027 to 2028 annual development programme, due with the Punjab budget in June 2027, which will show how much of the Rs18.862 billion the province plans to spend in the year after.

Share

Share to your story

Sized for Instagram Stories. The link is copied, ready for a link sticker.

Making your story imageA few seconds

Published 13 November 2026. Spotted an error? Write to contact@frontieredit.com.